Oyu Tolgoi Copper Project

Ivanhoe’s Qyu Tolgoi Copper Project progressing toward Start in 2013

30.03.2011 | Editor: Marcel Dröttboom

Construction of Ivanhoe’s Oyu Tolgoi Copper Project is progressing toward start of commercial production in the first half of 2013. (Picture: Ivanhoe Mines)

Vancouver (BC), Canada – Ivanhoe Mines announced that the construction of its Oyu Tolgoi Copper Project is progressing toward start of commercial production in the first half of 2013. A USD 2.3 billion budget has been approved for ongoing construction in 2011.

The Oyu Tolgoi Project initially is being developed as an open-pit operation, with the first phase of mining planned to start at the near-surface Southern and Central Oyu deposits. A copper concentrator plant, related facilities and necessary infrastructure that will support an initial throughput of 100000 tonnes of ore per day are being constructed to process ore scheduled to be mined from the Southern Oyu open pit. The ore will provide feed for the commissioning of the concentrator in advance of the planned start of commercial production of copper-gold-silver concentrate in the first half of 2013.

An 85000-tonne per day underground block-cave mining operation also is being developed at the Hugo North Deposit, with initial production expected to begin in 2015. The throughput capacity of the concentrator plant is expected to be expanded when the underground mine begins production.

Fluor Corporation is in charge of overall Oyu Tolgoi program management, as well as services related to engineering, procurement and construction management for the ore processing plant and mine-related infrastructure, such as roads, water supply, a regional airport and administration buildings.

USD 2.3 billion Capital Budget for ongoing Construction at Oyu Tolgoi Copper Project

In December 2010, Ivanhoe Mines announced that a USD 2.3 billion capital budget had been approved for 2011 in what will be the peak year of construction activity on the first phase of the Oyu Project.

In addition to the USD 2.3 billion capital budget, approval also was received for an additional USD 150 million budget for the 2011 Ulaanbaatar office operations, and USD 100 million for the second tax prepayment due to be made by June 30, 2011.

USD 3.5 billion to reach Start of Concentrator Commissioning in 2012

The 2011 project budget was approved after the Ivanhoe Mines and Oyu Tolgoi LLC boards and the joint Technical Committee reviewed current estimates of projected capital requirements through to project completion. The reviews included cash requirements from January 1, 2011, for the completion of the Southern Oyu open-pit mine; completion of the 100000-tonne-per-day concentrator; and advancing construction on elements of the Hugo North underground mine, including the Shaft #2 headframe, sinking of Shaft #2, completion of final design and ongoing development of the underground mine.

Total capital required for phase one – from January 1, 2011, to the start of commissioning of the ore processing plant is projected to be USD 3.5 billion. This includes approximately USd 2.9 billion to complete construction of the Southern Oyu open-pit mine, processing plant and essential infrastructure, including electrical power, water, roads, a paved airport runway and Mongolian-designed passenger terminal; it also includes taxes and continued underground development of the phase-two Hugo North mine.

Capital required from January 1, 2011, through to completion of the phase-one, 100,000-tonne-per-day project in 2013 is expected to total approximately USD 4.5 billion.

Principal Elements of 2011 Construction Program include:

Leave a comment

This article is protected by copyright. You want to use it for your own purpose? Infos can be found under www.mycontentfactory.de (ID: 373702)